April 10, 2025
Environmental surveys, Condamine floodplain, April 2025
Inland Rail contractors will complete various surveys around the Condamine floodplain in April to inform ongoing Inland Rail design refinements.
- April 2025 - April 2025
- Various locations
- Brookstead, Millmerran, Pampas

April 8, 2025
Utilities investigations, NSW/Qld Border to Whetstone, April 2025
Inland Rail contractors will complete utilities investigations at various locations between NSW/Qld border and Whetstone in Queensland. These investigations help to determine the location of underground utilities to help with the planning and scope of Inland Rail.
- April 2025 - April 2025
- Various locations
- Whetstone, Yelarbon, Kurumbul

March 6, 2025
NSW/Qld Border to Gowrie Geotechnical investigations April 2025
Geotechnical investigations are continuing in the Queensland Rail corridor, local roads and on private properties between the NSW/Queensland Border and Whetstone. Geotechnical investigations help to determine ground conditions through several testing methods.
- April 2025 - April 2025
- Existing rail corridor and local roads
- Whetstone, Yelarbon, Kurumbul

March 6, 2025
Meet the newest member of our team, Nat Woods
Late last year our Goondiwindi team moved into new office space at 28 Marshall Street, Goondiwindi, which is better suited for community drop-ins. Greeting visitors is our newest team member and a well-known and respected Goondiwindi local, Nat Woods.

December 20, 2024
NSW/Qld Border to Gowrie Section update – December 2024
As 2024 draws to a close, we’re reflecting on our achievements across the NSW/Qld Border to Gowrie section and thank all project communities for their continued cooperation, patience and feedback as we move closer to achieving environmental approvals.

November 28, 2024
NSW/Qld Border to Gowrie section overview
The NSW/Qld Border to Gowrie section is approximately 217km of new track to provide open access freight railway for Inland Rail. This Section Overview provides a summary of the section.

October 3, 2024
Get to know our NSW/Qld Border to Gowrie engagement team
Our stakeholder engagement teams are your link to understanding the 12 sections of Inland Rail. Meet the locally based team supporting our NSW/Qld Border to Gowrie section.

October 3, 2024
NSW/Qld Border to Gowrie Section update – October 2024
Inland Rail continues to progress the NSW/Qld Border to Gowrie section. In Queensland, we’re finalising the required environmental approvals, gaining land access to conduct site surveys and investigations, and securing land required for this section.

October 3, 2024
Inland Rail brings drone technology to Yelarbon State School
Our Inland Rail team recently visited Yelarbon State School for a fun and educational morning showcasing drone technology and how these devices are used on Inland Rail.

August 19, 2024
NSW/Qld Border to Gowrie Section update – August 2024
Inland Rail is still going ahead with the NSW/Qld Border to Gowrie section and neighbouring sections in northern NSW.