Penneys Road to Tapscott Road ongoing construction works

From 4 October 2023, our contractor Trans4m Rail will continue commissioning and finishing works within the rail corridor between Penneys Road, Bellata and Tapscott Road, Moree.

Stage 2 - Passing loop and siding south of Tapscott Road_ Moree. Looking south to Narrabri

Snapshot

Date

04 October 2023 - October 2023

Working hours

7am to 6pm, Monday to Sunday

Location

Between Penneys Road and Tapscott Road

Town
  • Bellata
  • Moree
Local Government Area
  • Moree Plains Shire Council

Work being done

Low impact activities associated with the works, such as machinery re-fueling, managing environmental controls and traffic control may occur outside of these hours.

Works will involve:

  • installing signage, fencing and landscaping
  • commissioning and finishing works.

What can I expect?

  • trucks and other vehicles will enter and exit the construction site via multiple access gates
  • construction machinery and equipment operating on site
  • delivery of materials and equipment
  • changed traffic conditions under traffic control.

Machinery used

  • hi-rail vehicles
  • excavators
  • loaders
  • watercarts.

How we’re managing impacts

Traffic control will be in place and water carts to assist in managing dust, where required.

Contact

Phone: 1800 732 761

Email: inlandrailnsw@artc.com.au

Post: Inland Rail, GPO Box 14, Sydney NSW 200