Service investigations – Edmondson Street, Wagga Wagga (rescheduled)

From August to September 2023, specialist contractors will undertake additional investigations on behalf of Inland Rail to locate and map underground utilities near Edmondson Street.

Snapshot

Date

August 2023 - September 2023

Working hours

7am to 6pm, Monday to Friday

8am to 1pm Saturdays

Location

Edmondson Street

Town
  • Wagga Wagga
Local Government Area
  • Wagga Wagga

Work being done

These investigations have been assessed through a Review of Environmental Factors under the Environmental Planning and Assessment Act 1979.

We want to reassure residents that starting these investigations now does not mean approval has been given for major construction to begin on the Albury to Illabo section.

They will however enable major construction to start more efficiently once approvals are issued.

Overview of investigations

  • Drilling of exploratory holes to confirm locations of utility lines.
  • Backfilling of drilled holes to restore ground condition.

Sites access roads used
Specific access requirements will be handled directly by the contractor.

What can I expect?

Minimal machinery and equipment operating on site.

Machinery used

  • Drill rig,
  • utility light vehicles and
  • vacuum truck.

How we’re managing impacts

Access to residential properties will be maintained at all times.

Contact

Phone:1800 732 761

Email: inlandrailnsw@artc.com.au

Post: GPO Box 14, Sydney NSW 2001