Beaconsfield Parade bridge works, Glenrowan
During July 2023, our contractor McConnell Dowell will continue works for the new Beaconsfield Parade bridge in Glenrowan.
Work being done
McConnell Dowell will continue construction of the new Beaconsfield Parade bridge in Glenrowan during July.
Works include installing bridge support structures, including concrete piers, on the Woolshed Road and Siege Street sides of the track. This includes excavating and concreting around the existing piles.
The team will also prepare for construction of retaining walls at each end of the bridge.
What can I expect?
- Works will occur between 7am and 6pm weekdays with potential Saturday works between 7am and 1pm
- Construction noise during the day
- Heavy machinery and equipment operating onsite
- Delivery of materials and equipment
- Trucks and other vehicles entering and exiting the construction site may cause minor traffic delays
- Some of these works will be noisy and mitigation measures will be in place
- Beaconsfield Parade bridge reduced to one lane with traffic lights to manage traffic flow
- Beaconsfield Parade closed between Siege Street and Church Street
- Beaconsfield Parade bridge traffic speed reduced to 40km/h
- Limited access to the northern end of Woolshed Road other than to local businesses and residents.
Machinery used
- Trucks,
- cranes,
- excavators,
- concrete trucks,
- loaders, and
- light vehicles
will be used within the works area.
How we’re managing impacts
- Water carts will be onsite to wet down areas to assist in managing dust
- traffic controls will be in place, where required, including Variable Message Signage (VMS) boards
- live monitoring of noise, dust and vibration.
Contact
Thank you for your patience and cooperation while we carry out these works.