Hamilton Street, Broadford services investigation works

Throughout December 2022, specialist contractors will conduct non-destructive water bore drilling works to locate and map underground services in and around Hamilton Street, Broadford.

Snapshot

Date

December 2022 - December 2022

Working hours

7am to 6pm, seven days a week

Location

Hamilton Street, Broadford

Town
  • Broadford
Local Government Area
  • Mitchell Shire Council

Work being done

Specialist contractors will conduct non-destructive water bore drilling works to locate and map underground services in and around Hamilton Street, Broadford.

A mobile drill will be set up in Hamilton Street, High Street Service Road and Ferguson Street.

During works, there will be temporary restricted access to some properties. However, work crews will ensure local residents and businesses can access their driveways upon request.

Residents and motorists are asked to take care and observe all traffic management instructions and signage.

What can I expect

  • Traffic management in and around where works are occurring
  • Reduced speed limits of 40km near works
  • Mobile machinery and equipment operating onsite
  • Bore drilling to take place for about two hours at each site
  • Nearby residents can expect some noise during daylight hours
  • The drilling process will create small holes in the ground which will be filled in at the completion of the works.

Machinery used

  • Small drill rig,
  • support vehicles,
  • traffic management equipment and
  • signage.

How we’re managing impacts

  • Traffic management will be in place to ensure safe access for all road users
  • Reduced road speeds in the vicinity of the works
  • Mobile drilling equipment will ensure property access can be maintained upon request.

Contact

Phone: 1800 732 761

Email: victoriaprojects@artc.com.au 

Post: 39 Bakehouse Road, Kensington, Vic 3031

Mobile work sites in Hamilton Street, Ferguson Street and High Street Service Road, Broadford


Share: