Murray Valley Highway works Barnawartha North

Throughout October 2023, McConnell Dowell will continue undertaking construction works for the Inland Rail project near Murray Valley Highway, Barnawartha North.

Snapshot

Date

October 2023 - October 2023

Working hours

7am-6pm weekdays
7am-1pm Saturdays

Location

Barnawartha North

Town
  • Barnawartha North
Local Government Area
  • Wodonga City Council

Work being done

McConnell Dowell will continue undertaking construction works near the Murray Valley Highway, Barnawartha North.

Works include the final concreting of the retaining wall around the lowered section of track, some fencing reinstallation around the works area, minor drainage works and the tidying up of the area after recent major excavation works.

What can I expect?

  • traffic management and reduced speeds will be in place during some works, which may cause minor traffic delays
  • construction noise during daylight hours with mitigation measures in place
  • ground excavation at various locations
  • trucks and other vehicles entering and exiting the construction site, may cause minor traffic delays
  • heavy machinery and equipment operating onsite
  • delivery of materials and equipment.

Machinery used

  • trucks,
  • cranes,
  • excavators,
  • concrete trucks,
  • loaders and
  • light vehicles

will be used within the works area.

How we’re managing impacts

  • water carts onsite to wet down areas to assist in managing dust
  • traffic management in place to ensure safe access for all road users where required
  • environmental controls in place.

Contact

Phone: 1800 929 244
Email: victoriaprojects@artc.com.au
Post: 39 Bakehouse Road, Kensington, Vic 3031

Barnawartha North work areas displayed in blue

Construction map for Barnawartha North works


Share: