North East Rail Line shutdown – signalling works
From 18 to 20 March 2023, our contractor McConnell Dowell will undertake works in preparation for new Inland Rail signalling infrastructure that allows sufficient clearance for double-stacked freight trains.
Work being done
Works will be undertaken along the North East Rail Line and include preparing foundations for the installation of new signal gantries and the removal of surplus equipment and structures.
What can I expect?
- Construction noise during the day and potential night works
- Use of generators and light towers (these will be directed away from residential properties where possible)
- Trucks and other vehicles entering and exiting construction sites, which may cause minor traffic delays
- Heavy machinery and equipment operating onsite
- Delivery of materials and equipment.
Machinery used
- Trucks,
- cranes,
- excavators,
- concrete trucks,
- loaders, and
- light vehicles
will be used will be used within the work areas.
How we’re managing impacts
- Water carts will be onsite to wet down areas to assist in managing dust
- Traffic controls will be in place, where required
- Directing light towers away from residential properties.