Seymour site compound establishment works
Throughout November, McConnell Dowell will undertake site compound establishment works, utility service relocations and continue construction of a new temporary access road for Granville Drive.
Work being done
In preparation for the replacement of the Seymour-Avenel Road bridge at Seymour, McConnell Dowell will undertake site compound establishment works, utility service relocations and continue construction of a new temporary access road for Granville Drive during November.
Works will involve delivery of materials and site compound equipment and approved vegetation removal.
What can I expect?
- works will occur 7am-6pm on weekdays
- construction noise during daylight hours with mitigation measures in place
- speed restrictions will be in place along Seymour-Avenel Road and Granville Drive until bridge construction commences
- trucks and other vehicles entering and exiting the construction site, may cause minor traffic delays
- approved vegetation removal in the project area
- heavy machinery and equipment operating onsite
- delivery of materials and equipment.
Machinery used
- trucks,
- woodchippers,
- loaders and
- light vehicles
will be used within the works area.
How we’re managing impacts
- water carts will be onsite to wet down areas to assist in managing dust
- traffic management will be in place to ensure safe access for all road users where required
- environmental controls in place.
Contact
Thank you for your patience and cooperation while we carry out these works.