Camurra to Milguy level crossing upgrades

Our contractor Trans4m Rail will continue level crossing and drainage upgrade works at Roydon Road, Wongabindie Road and Calimpa Road, north of Camurra, from Friday 7 January 2022.

Snapshot

Date

07 January 2022 - March 2022

Working hours

7am to 6pm, seven days a week

Location

Level crossings 1842, 909 and 910 at Roydon Road, Wongabindie Road and Calimpa Road, north of Camurra

Town
  • Camurra
  • Milguy
Local Government Area
  • Moree Plains Shire

Work being done

Works will include installing new drainage structures and upgrades at level crossings 1842, 909 and 910.

Motorists are urged to follow changing traffic conditions on site, including speed zone reductions and directional traffic signage.

What can I expect

  • Trucks and other vehicles entering and exiting the construction site
  • Construction machinery and equipment operating on site adjacent to live traffic along associated local roads
  • Delivery of materials and equipment to site
  • Some of these works will be noisy and mitigation measures will be in place.

Some minor traffic delays are expected during work hours and we thank you in advance for your patience.

Machinery used

  • Trucks
  • cranes
  • graders
  • excavators
  • loaders
  • rollers
  • water / vacuum excavation trucks.

How we’re managing impacts

  • Traffic control will be in place, where required
  • Water carts will be on site to wet down areas to assist in managing dust.

Contact

Phone: 1800 732 761

Email: inlandrailnsw@artc.com.au

Post: Inland Rail, GPO Box 14, Sydney NSW 2001