Level crossing works, Roydon Road, Moree, 11-19 March, 2025
Rhomberg Sersa Australia Pty Ltd (RSA) has been engaged to undertake level crossing works at Roydon Road, near Moree, between 11 March and 19 March 2025. Access across the Roydon Road level crossing will be maintained during the work. Please note: This work has been postponed due to the weather.

Work being done
RSA will carry out a range of activities including replacement of the level crossing rubber panel system.
To minimise disruptions to train services and road users, work will be undertaken on half of the level crossing at a time, and the work site protected behind traffic barriers.
Low impact activities associated with the works, such as delivery of plant, re-fuelling, managing environmental controls and traffic control may occur outside of these hours.
What can I expect?
- Trucks and other vehicles entering and exiting the work site.
- Construction machinery and equipment operating on site adjacent to live traffic.
- Some minor traffic delays are expected during work hours.
How we're managing impacts
- The works at the level crossing will be undertaken in two halves so access across the level crossing can be maintained at all times.
- Traffic control will be in place and an alternating lane of traffic across the rail line will be maintained at all times.
- Lighting of the work site at night will be directed at the worksite and away from any nearby residents.
- Access to private properties will not be impacted.
Cancellation of works
Works can sometimes be cancelled at short notice depending on weather and other factors. Should this occur, works will be rescheduled. Signage on site will advise of any changes.
Contact
For any concerns or enquiries phone the team on 1800 732 761 or email inlandrailnsw@inlandrail.com.au.