Yamboon Lane level crossing upgrade

Our contractor Trans4m Rail will undertake level crossing and drainage upgrade works on Yamboon Lane (Crooble Road), south of Croppa-Moree Road, from Friday 7 January 2022.

Snapshot

Date

07 January 2022 - March 2022

Working hours

7am to 6pm, seven days a week

Location

Level crossing 916 on Yamboon Lane (Crooble Road), south of Croppa-Moree Road

Town
  • Croppa Creek
Local Government Area
  • Moree Plains Shire

Work being done

Works will include installing new drainage structures and upgrades at level crossing 916.

Motorists are urged to follow changing traffic conditions on site, including speed zone  reductions and directional traffic signage.

What can I expect

  • Trucks and other vehicles entering and exiting the construction site
  • Construction machinery and equipment operating on site adjacent to live traffic along Yamboon Lane (Crooble Road)
  • Delivery of materials and equipment
  • Some of these works will be noisy and mitigation measures will be in place
  • Some minor traffic delays are expected during work hours.

Machinery used

  • Trucks
  • cranes
  • graders
  • excavators
  • loaders
  • rollers
  • water/vacuum excavation trucks.

How we’re managing impacts

  • Traffic controls will be in place, where required.
  • Water carts will be on site to wet down areas to assist in managing dust.

Contact

Phone: 1800 732 761

Email: inlandrailnsw@artc.com.au

Post: Inland Rail, GPO Box 14, Sydney NSW 2001

Map

Yamboon Lane (Crooble Road) level crossing upgrade (construction impact zone shown in green/yellow).
Map showing level crossing works at Yamboon Lane (Crobble Road) NSW 2411