Utilities relocations – Gowrie Junction, July-November 2024
From 17 July 2024, Telstra will carry out work to relocate underground telecommunication cables for the Gowrie to Helidon section of Inland Rail.
Work being done
- Relocation of underground telecommunication cables.
From 17 July 2024, construction activity will start from the corner of Gowrie Junction Road and Ganzers Road and progress along Krienke Road.
The work will predominantly occur in road reserve; however, some access to private properties will be required. Telstra has notified impacted property owners in accordance with the requirements of the Telecommunications Act 1997.
What can I expect?
- Delivery trucks and other vehicles in the Gowrie Junction area to support the works
- Construction machinery and equipment operating
on site - Increased noise.
Machinery used
Vacuum trucks, directional boring machine, earth moving equipment, tip trucks, light vehicles.
How we’re managing impacts
- Works will have no impact on landowner access
- Traffic control will be in place, where required
- If additional out-of-hours work is required, nearby residents will be notified.
Contact
Phone: 1800 732 761
Email: inlandrailqld@inlandrail.com.au
Thank you for your patience and cooperation while we carry out these works.