Billy Hughes bridge telecommunications service relocation
Between March 2023 and May 2023, utility contractors will undertake early works on ARTC Inland Rail’s behalf to relocate telecommunication services in the vicinity of Billy Hughes bridge.
Work being done
These early works have been assessed through a Review of Environmental Factors under the Environmental Planning and Assessment Act 1979.
We want to reassure residents that starting these early works now does not mean approval has been given for major construction to begin on the Albury to Illabo section.
Completing early works before the Albury to Illabo project obtains approval from the Department of Planning and Environment means we can start major construction more efficiently once approvals are issued.
Overview
- Relocate existing and install new telecommunication cables and cable pits in the vicinity of Billy Hughes bridge and Wagga Road.
What can I expect
- Construction machinery and equipment operating on site
- Delivery of materials and equipment to site
- Temporary service interruptions may be required. Impacted residents will be notified in advance
Sites access roads used
Construction contractors will access the work sites from Wagga Road.
Machinery used
- Vacuum trucks,
- trucks,
- water cart,
- flood lights,
- generator,
- welding equipment,
- hand tools,
- equipment,
- excavators,
- skid steer (loader with wheels) or Positrack (loader with tracks),
- directional drilling/boring machine,
- light vehicles.
How we’re managing impacts
Traffic management will be in place to ensure safe access for all road users where required.