Yallaroi Creek rail bridge replacement

Trans4m Rail will conduct rail bridge demolition and replacement works near Yallaroi Creek and Boonery Park Road, south of North Star, between April and September 2021.

Yalleroi creek bridge works notifications

Snapshot

Date

April 2021 - September 2021

Working hours

Between 7am and 6pm, Monday to Saturday

Location

Yallaroi Creek Bridge, near Boonery Park Road south of North Star

Town
  • North Star, NSW
Local Government Area
  • Gwydir Shire Council

Work being done

The works will involve construction of temporary road access from Boonery Park Road to the bridge. Demolition will include removal of the existing bridge structure and concrete components. The bridge replacement will commence following demolition.

A temporary access road, west of level crossing 921 near Boonery Park Road, will be used to access the site during these works.

What to expect

  • Trucks and other vehicles will enter and exit the construction site via Boonery Park Road, west of level crossing 921
  • Construction machinery and equipment operating on site
  • Delivery of materials and equipment
  • Motorists should follow traffic controls and drive with caution
  • There may be some noise associated with these works

Machinery used

Trucks, cranes, graders, excavators, loaders, rollers and water / vacuum excavation trucks will be used within the construction impact zone.

How we’re managing impacts

  • Traffic control will be in place, where required.
  • Water carts will be on site to wet down areas to assist in managing dust.

Contact

Phone: 1800 732 761

Email: inlandrailnsw@artc.com.au

Post: Inland Rail, GPO Box 14, Sydney NSW 2001