The Narrabri to North Star section of Inland Rail will upgrade 189km of existing rail corridor and construct approximately 2km of new track near Moree, New South Wales.
This is the second section of Inland Rail to enter construction, following the commissioning of the Parkes to Narromine line, in September 2020.
Narrabri to North Star crosses the three local government areas of Gwydir, Narrabri and Moree Plains. Due to its scale and complexity, it’s broken into two stages to enable first phase construction to begin while planning and environmental approvals are gained for the second phase.
Phase 1: Narrabri North to North Star
Major construction on the Narrabri to North Star Phase 1 section is now complete.
Work involved upgrading 176km of track along the existing corridor.
Trans4m Rail, a joint venture between contractors John Holland and SEE Civil, was the principal contractor for Phase 1 works.
View the Phase 1 Operations Fact Sheet
For all queries related to the operational rail corridor and fencing, contact the ARTC Community Line on 1300 550 402, or email community@artc.com.au.
Phase 2: Moree to Camurra
The Phase 2 section includes upgrading approximately 13km of track from Alice Street, Moree across the Gwydir floodplain to the eastern side of the Moree Gun Club. It also includes approximately 2km of new track at Camurra, north of Moree.
Snapshot
Type
Upgrade and new track
Length
189km upgrade track
approximately 2km new track
Anticipated works
Upgrading existing track and building new track to bypass hairpin turn
Status
Narrabri to North Star Phase 1
Narrabri to North Star Phase 2
Take care – trains are now in operation
Major construction on the Phase 1 section is now complete and trains are operating between Narrabri and North Star. We’ve improved safety at 57 level crossings along the alignment, including upgrading 10 passive level crossing to active with bells, lights and boom gates.
For all queries related to the operational rail corridor and fencing, contact the ARTC Community Line on 1300 550 402, or email community@artc.com.au.
Please take extra care at level crossings and obey all signage, signals and boom gates
Project map
The track begins in Narrabri, passing through Edgeroi, Bellata, Gurley, Moree, Camurra, Crooble, Milguy, Croppa Creek and on to North Star.
Phase 1: Narrabri North to North Star
Phase 1 includes upgrading 176km of track along the existing rail corridor.
Trans4m Rail, a joint venture between contractors John Holland and SEE Civil, is the principal contractor for Phase 1 works.
Phase 2: Moree to Camurra
The Phase 2 section includes upgrading approximately 13km of track from Alice Street, Moree across the Mehi-Gwydir floodplain to the eastern side of the Moree Gun Club.
It also includes approximately 2km of new track at Camurra, north of Moree.