Camurra to North Star ongoing major construction works
Our contractor Trans4m Rail will continue track construction works from Friday 7 January 2022 within the rail corridor between Camurra and North Star.
Work being done
Works will occur between 7am and 6pm Monday to Sunday to ensure our construction schedule is maintained. Please note, Sunday working hours are permitted under the project’s environmental approvals.
What can I expect
- Trucks and other vehicles will enter and exit the construction site via access gates
- Changed traffic conditions will be in place at level crossings
- Construction machinery and equipment operating on site
- Delivery of materials and equipment to site
- Machinery re-fuelling, managing environmental controls and traffic control may also occur outside of work hours
- Motorists should follow traffic controls and drive with caution.
Machinery used
- Hi-rail vehicles
- trucks
- articulated dump trucks
- graders
- scrapers
- excavators
- loaders
- dozers
- stabilisers
- posi-tracks
- compactors
- rollers
- water / vacuum excavation trucks.
How we’re managing impacts
- Traffic control will be in place, where required
- Water carts will be on site to wet down areas and assist in managing dust.
Contact
Phone: 1800 732 761
Email: inlandrailnsw@artc.com.au
Post: Inland Rail, GPO Box 14, Sydney NSW 2001