From January to March 2023, our contractor Trans4m Rail will continue to undertake level crossing and drainage upgrade works on Crooble Road, Crooble.

Snapshot

Date

January 2023 - March 2023

Working hours

7am to 6pm, seven days a week

Location

Crooble Road

Town
  • Crooble
Local Government Area
  • Gwydir Shire

Work being done

Works will include installation of signage, sealing of the level crossing and general maintenance work.

To facilitate the works, a temporary road has been constructed to divert traffic around the existing level crossing. The temporary gravel access road will accommodate road trains.

What can I expect

  • Trucks and other vehicles entering and exiting the construction site
  • Construction machinery and equipment operating on site
  • Delivery of materials and equipment
  • Some of these works will be noisy and mitigation measures will be in place
  • Minor traffic delays are expected during work hours.

Machinery used

  • Trucks,
  • cranes,
  • graders,
  • excavators,
  • loaders,
  • rollers and
  • water/vacuum excavation trucks

will be used within the construction impact zone.

How we’re managing impacts

  • Traffic control will be in place, where required
  • Water carts will be on site to wet down areas to assist in managing dust.

Contact

Phone: 1800 732 761

Email: inlandrailnsw@artc.com.au

Post: Inland Rail, GPO Box 14, Sydney NSW 2001


Share: