Narrabri to North Star construction look-ahead
Bridge replacement works continue at Gil Gil Creek, Gurley Creek, Croppa Creek and Yallaroi Creek. Meanwhile, construction of a laydown area for the temporary storage of equipment and supplies to ensure accessibility and safe movement for vehicles and machinery will commence at Bellata.
August 31, 2021

August – October 2021
We are committed to the safe delivery of Inland Rail during this unprecedented Covid-19 pandemic, and we are taking extra precautions and implementing additional preventatives measures to ensure the safety of our team and the Moree and Narrabri communities. These include limiting non-essential travel by staff and ensuring all workers compliant with all NSW health restrictions and the project adheres to a strict Covid Safe plan.
Works occurring between Penneys Road and Gurley Creek, and Tycannah Creek to Tapscott Road include:
- Ongoing delivery of culverts at Gurley
- Track laying
- Rail welding and tampering
- Installation of ballast
- Track resurfacing
- Landscaping
- Level crossing works, including signalling
- Commissioning.
- Track stripping
- Excavation of existing formation material
- New culvert installation
- Lime stabilisation of new layers
- Establishing a satellite office in Croppa Creek
- Surveying of alignment continues
- Delivery of culverts at the Crooble laydown area.