North of Narrabri to Penneys Road ongoing construction works

From 4 October 2023, our contractor Trans4m Rail will continue commissioning and finishing works within the rail corridor between the Plant Breeding Institute, north of Narrabri and Penneys Road, Bellata.

Explorer passenger train travelling south to Narrabri. Photo is looking south to Narrabri

Snapshot

Date

04 October 2023 - October 2023

Working hours

7am and 6pm, Monday to Sunday

 

Location

North of Narrabri to Penneys Road

Town
  • Narrabri
  • Bellata
Local Government Area
  • Narrabri Shire Council

Work being done

Low impact activities associated with the works, such as machinery re-fueling, managing environmental controls and traffic control may occur outside of these hours.

Works will involve:

  • installing signage, fencing and landscaping
  • commissioning and finishing works including corridor clean up.

What can I expect?

  • trucks and other vehicles will enter and exit the construction site via multiple access gates
  • construction machinery and equipment operating on site
  • delivery of materials and equipment
  • changed traffic conditions under traffic control.

Machinery used

  • hi-rail vehicles
  • excavators
  • loaders
  • watercarts.

How we’re managing impacts

Traffic control will be in place and water carts used to assist in managing dust, where required.

Contact

Phone: 1800 732 761
Email: inlandrailnsw@artc.com.au
Post: Inland Rail, GPO Box 14, Sydney NSW 2001