Temporary traffic changes at Kanimbla and Gurley Creek Roads

From early September 2021, Trans4m Rail will continue major track construction works within the existing rail corridor between Bellata and South Moree in preparation for rail operations to recommence from 1 November 2021.

Rail track

Snapshot

Date

September 2021 - October 2021

Working hours

7am to 6pm, seven days a week

Location

Near Kanimbla Road and Gurley Creek Road, between Bellata and South Moree

Town
  • Moree, NSW
  • Bellata, NSW
Local Government Area
  • Moree Plains Shire

To enable level crossing works at Kanimbla Road (LX553) and Gurley Creek Road (LX554), traffic restrictions (including temporary lane closures) will be in place for the duration of works. These activities may result in minor travel delays and we apologise in advance for any inconvenience caused.

For public safety, road users should observe all traffic control instructions, signage and VMS boards during this period.

Works will occur between 7am and 6pm Monday to Sunday. Low impact activities such as machinery re-fuelling, managing environmental controls and traffic control may also occur outside of these hours. Residents will be notified in advance of any out-of-hours work.

Work being done

  • Delivery of ballast via ballast train
  • installation of kerbing
  • installation of final road surface and line markings
  • installation of rubber level crossing matting
  • road safety audit at completion of works.

Machinery used

  • Hi-rail vehicles (rolling stock)
  • trucks
  • graders
  • excavators
  • posi-tracks
  • rollers
  • water / vacuum excavation trucks.

How we’re managing impacts

  • Traffic control and signs will be in place, where required
  • water carts will be on site to wet down areas to assist in managing dust.