Track formation trials near Gurley
Trans4m Rail will conduct track formation trials near Gurley NSW over a two-week period starting 14 January 2021. The initial trial will involve removing the siding rail and embankment and replacing it with lime stabilised fill.

What to expect
Hi-rail vehicles, trucks, graders, scrapers, excavators, loaders, stabilisers, rollers and water / vacuum excavation trucks will be used within the construction impact zone.
How we’re managing impacts
We will implement a vehicle movement plan for construction traffic and use water carts to manage dust, as required.