Night works, Roy Street East, Wangaratta, 15-25 January

Telstra relocation works are being undertaken prior to the construction of Green Street bridge as the services will be impacted by the new bridge structure. Telstra and TPG will complete the connections. These works are being undertaken at night to limit the impact of service outage to customers.

Snapshot

Date

15 January 2024 - 25 January 2024

Working hours

Night works will be conducted from:

  • Midnight Monday, 15 January to 6am Tuesday, 16 January
  • Midnight Tuesday, 16 January to 6am Wednesday, 17 January
  • Midnight Wednesday, 24 January to 6am Thursday, 25 January
Location

Roy Street East, Wangaratta

Town
  • Wangaratta
Local Government Area
  • The Rural City of Wangaratta

Work being done

Works include disconnecting redundant cables and connecting new cables.

The work will occur within the rail corridor.

Telstra will notify their customers directly of any anticipated impacts to services.

What can I expect

  • Light vehicles entering and exiting the construction site
  • Light towers directed at the ground works
  • Noise from vehicles and light tower motors.

Machinery used

Light vehicles and light towers.

How we’re managing impacts

  • Performing night works to limit Telstra service outage
  • Reducing vehicles required onsite.

Contact

Phone: 1800 929 244

Email: victoriaprojects@artc.com.au

Mail: 39 Bakehouse Road, Kensington, Vic 3031

 

Thank you for your patience and cooperation during this activity.

 

Map of Roy St East, Wangaratta, displaying where work will be done by 22 December.


Share: