Site investigations, Illabo to Stockinbingal, 6-31 January, 2025

From Monday, 6 January, Inland Rail will be undertaking site investigations as part of the Inland Rail Illabo to Stockinbingal project in New South Wales.

Current design at Ironbong Road, for the Illabo to Stockinbingal project, NSW

Snapshot

Date

06 January 2025 - 31 January 2025

Working hours
  • 7am-6pm Monday to Saturday.
Location

Multiple locations

Town
  • Illabo
  • Stockinbingal
Local Government Area
  • Junee Shire Council
  • Cootamundra-Gundagai Regional Council

Work being done

As part of the construction, site investigations are required to provide essential information to assist with planning. Inland Rail’s contractor, John Holland, will undertake work as part of these investigations including survey, utility, contamination and geotechnical (excavation and drilling) investigations.

Activities will include:

  • Initial site walk-over to plan for the following activities
  • Surveying the project/property boundaries, road and pavement levels at multiple locations.
  • Underground and overhead utility locating and mapping using non-destructive digging (NDD)
  • Geotechnical investigation works including drilling and soil sampling
  • Environmental investigations through inspection and monitoring activities.

Work locations

Work will occur at various locations within the project boundaries and will be discussed with individual property owners / lessees prior to commencement.

What can I expect?

  • Works 7am-6pm Monday to Saturday.
  • Property owners will be contacted regarding access prior to works
  • Traffic management may be required in some locations where works are occurring close to roads or for safe access. Please observe all traffic management instructions and signage
  • Reduced speed limits of down to 40km/h near works
  • Workers using machinery, equipment, hand tools and service vehicles operating at each site
  • Nearby residents may hear some noise during these works and can expect some additional construction workers and vehicles in the area.

Machinery used

Excavators, drill rigs, small truck mounted drill rig, NDD truck, water carts and support vehicles, workers using hand tools and survey equipment, traffic management equipment and signage.

How we're managing impacts

  • Traffic management and reduced road speeds
  • Environmental controls in place
  • Access to private properties will be maintained
  • Temporary fencing around excavation sites.

Cancellation of works

Works can sometimes be cancelled at short notice depending on weather and other factors. Should this occur, works will be rescheduled.

Contact

For any concerns or enquiries phone 1800 732 761 or email inlandrailnsw@inlandrail.com.au.

Thank you for your patience and cooperation while we carry out these works.