Level crossing works, Boonery Park Road, North Star, 29 April – 7 May 2025

Rhomberg Sersa Australia Pty Ltd (RSA) has been engaged to undertake level crossing works on the Inland Rail alignment at Boonery Park Road, North Star, between 29 April and 7 May 2025.

Snapshot

Date

29 April 2025 - 07 May 2025

Working hours

Working hours are between 6.30am and 6.30pm. Crews will be on site until works are completed.

Location

Boonery Park Road

Town
  • North Star
Local Government Area
  • Gwydir Shire Council

Work being done

RSA will carry out a range of activities including replacement of the level crossing rubber panel system.

The level crossing will be closed to traffic for the duration of the works and a detour will be in place.

Traffic will be diverted via Tumba Road and Croppa Creek Road. Access to Boonery Park Road will be maintained.

Please refer to map of the detour.

What can I expect?

  • Trucks and other vehicles entering and exiting the work site
  • Construction machinery and equipment operating on site adjacent to live traffic
  • Traffic management and detour signage.

How we're managing impacts

  • Detour signage and Variable Message Signs (VMS board) to assist with traffic management during the road closure
  • Lighting of the work site at night will be directed at the worksite and away from any nearby residents.
  • Access to private properties will not be impacted.

Cancellation of works

Works can sometimes be cancelled at short notice depending on weather and other factors. Should this occur, works will be rescheduled. Signage on site will advise of any changes.

Contact

For any concerns or enquiries phone the team on 1800 732 761 or email inlandrailnsw@inlandrail.com.au

Thank you for your patience and cooperation while we carry out this essential work.