Inland Rail’s Victorian sites double-stack ready
Inland Rail has hit a major milestone, with all 12 Victorian enhancement sites between Beveridge and Albury now ready for the operation of double-stacked freight trains.
November 23, 2026
The Tallarook passing loop, the last of the key sites to be double-stacked ready, was commissioned and returned to service earlier this week after six months out of action.
Passing loops are a parallel section of track connected to a single-track rail line that allow trains to safely pass or overtake each other.
A 1.15-kilometre section of the loop was lowered by 2.1 metres under the Hume Freeway. The work involved removing 4000 tonnes of material, replacing it with 4000 tonnes of ballast and laying 1650 new sleepers.
Inland Rail and construction partner John Holland are continuing the railway station transformations at Euroa and Benalla and applying the finishing touches to bridges in Broadford and Wandong.

Passing loop with machinery Tallarook, Victoria
Work began on the Beveridge to Albury Tranche 1 project in March 2023 with tracks lowered and bridges replaced at Barnawartha North, Glenrowan and Seymour Avenel Road, and the railway station upgraded at Wangaratta.
The Beveridge to Albury Tranche 2 project began in June 2024 and is closing in on completion, with major bridge replacements or station upgrades at Wandong, Hume Freeway – Tallarook, Hume Freeway – Seymour, Broadford, Euroa, and Benalla due to be completed before the end of the year.
Inland Rail Chief Executive Officer, Dr Sean Sweeney said:
“Reaching double-stack readiness at the main Beveridge to Albury sites is an important moment for Inland Rail.
“The achievements on B2A come from a lot of hard work, consultation and cooperation with our contractors, key stakeholders and local communities.
“We thank the local communities along the Beveridge to Albury alignment for their patience and understanding as we push to finalise all major works before the end of the year.”
Media enquiries: Phone 1300 196 401 Email: artcmedia@artc.com.au