News

May 11, 2026

Inland Rail’s ‘super possession’ a success in Victoria

Five additional Inland Rail sites at Wandong, Short Street - Broadford, Seymour, Euroa and Benalla can now accommodate double-stacked freight trains after the latest 86-hour ‘super possession’ was completed in Victoria.

News

February 23, 2026

Nailing it! Inland Rail uses soil nails to stabilise slopes

Inland Rail works in Broadford, Euroa and Tallarook are using soil nails to stabilise slopes and construction areas as part of the Beveridge to Albury Tranche 2 project.

Media release

November 27, 2025

Construction kicks off at Tallarook, Victoria

Inland Rail has used a 15-hour closure of the Albury line to carry out essential construction works on its Victorian sites, as the project moves towards completing the Beveridge to Parkes section by 2027.

News

March 28, 2025

In pictures: John Holland successfully completes works during 60-hour possession

Our construction partner John Holland undertook works across eight sites during a 60-hour track possession in March.

Media release

March 19, 2025

Inland Rail track possession prepares sites for major construction in Victoria

Inland Rail will use the upcoming 60-hour closure of the Albury, Shepparton and Seymour lines to carry out important construction activity and prepare sites on the Beveridge to Albury section of the project for major works later in the year.

News

August 29, 2024

John Holland inspection blitz between Wandong and Seymour

Our construction partner John Holland will undertake an inspection blitz from Friday 30 August to the early hours of Monday 2 September between Wandong and Seymour.

Map

June 1, 2024

Inland Rail in Victoria: Works Map

This is a map of the Inland Rail Beveridge to Albury section featuring the 12 project sites and works being undertaken.

You can find archived documents in the Info Hub Archive