Powerline works, Euroa, 8 November to 17 December 2024

To enable the safe running of double-stacked freight trains, additional height clearance between the rail and powerlines is required in some locations along the North East rail line.

Snapshot

Date

08 November 2024 - 17 December 2024

Working hours

Works 7am-7pm intermittently between 8 November and 17 December 2024.

Main works will occur week commencing 8 November and then week commencing 13 December 2024.

Location

Railway and Frost Streets

Town
  • Euroa
Local Government Area
  • Strathbogie Shire Council

Work being done

Inland Rail contractor McConnell Dowell will replace some power poles and relocate power lines underground within Frost Street and Railway Street, Euroa to create the required clearance.

Map showcasing the area of the works as described in the text

What can I expect?

  • Construction noise during the day
  • Traffic management and reduced speeds will be in place during some works, which may cause traffic delays
  • Small sections of road closures around the work zone, with detours in place during some works
  • Heavy machinery and equipment operating onsite
  • Delivery of materials and equipment
  • Homes with overhead power cable connections may require testing at the point of supply to ensure no reconnection issues after power outages.

Any directly affected properties will be notified by AusNet if interruptions to power supply are expected

Machinery used

Power trucks, elevated work platform, crane, excavator, drill rig, heavy and light vehicles will be used within the works areas.

How we're managing impacts

Traffic management will be in place to ensure safe access for all road users and pedestrians, where required.

Contact

For any concerns or enquiries please phone 1800 929 244 or email inlandrailvic@inlandrail.com.au.

Thank you for your patience and cooperation while we carry out these works.

 


Share: