Seymour-Avenel Road bridge works, Seymour, December 2024 – January 2025

Inland Rail contractor McConnell Dowell will continue works in and around the Seymour-Avenel Road bridge site in Seymour during December 2024 and January 2025.

Snapshot

Date

01 December 2024 - 31 January 2025

Working hours

Construction work 7am-6pm Monday to Friday and 7am-5pm weekends.

Location

Seymour-Avenel Road bridge

Town
  • Seymour
Local Government Area
  • Mitchell Shire Council

Work being done

  • Seymour-Avenel Road and Granville Drive construction including asphalting and line marking
  • Removal of the temporary section of Granville Drive
  • Bridge deck finishing works
  • Landscaping

What can I expect?

  • Construction noise during daylight hours, with mitigation measures in place
  • Changes to Granville Drive access with the completion of permanent road works, allowing the removal of the temporary road. Traffic management will be place
  • Business and local traffic access to Granville Drive will be maintained
  • Trucks and other vehicles entering and exiting the construction site, may cause minor traffic delays
  • Approved vegetation removal within the project area
  • Heavy machinery and equipment operating onsite
  • Delivery of materials and equipment
  • Seymour-Avenel Road bridge closed, with detour in place via Avenel Road.

Machinery used

Heavy and light vehicles including trucks, concrete trucks and pumps, cranes, loaders, excavators and rollers will be used within the works area.

How we're managing impacts

  • Water carts will be onsite to wet down areas to assist in managing dust
  • Traffic management in place to ensure safe access for all road users and pedestrians, where required
  • Environmental controls in place.

Contact

For any concerns or enquiries please phone 1800 929 244 or email inlandrailvic@inlandrail.com.au.