Wangaratta Railway Station and Green Street bridge works June 2024

Inland Rail will continue construction in and around Wangaratta Railway Station and Green Street bridge during June.

Works map

Snapshot

Date

June 2024 - June 2024

Working hours

7am-7pm Monday to Sunday (7 days)

Location

Wangaratta Station precinct

Town
  • Wangaratta
Local Government Area
  • The Rural City of Wangaratta

Work being done

At the station precinct there will be drainage and utility installations, as well as works including excavations for the pedestrian stairs, ramp and lift shaft on the eastern side of the station.

A pump station for the pedestrian underpass will continue to be installed, along with stairs and fencing for the new western platform.

Works on the new Green Street bridge will include concrete strengthening for the east abutment and footpath retaining wall and concreting spaying (shotcreting) on the west abutment.

Construction of a crane pad and deck superstructure assembly area will commence, in preparation for the upcoming lifting of the new bridge structure.

Works map

Works areas during June 2024.

What can I expect?

  • Construction work 7am-7pm Monday to Sunday (7 days)
  • Noise from construction machinery and equipment operating onsite
  • Trucks and other vehicles entering and exiting the work site
  • Ground excavations in various locations
  • Approved vegetation removal within the project area including tree removal in Roy Street West
  • Changes to pedestrian access via the Docker Street footbridge are in place
  • Green Street bridge closed between Norton Street and Roy Street West, with detours in place
  • Traffic management in and around Green Street, Cusack Street, Roy Street West, Spearing Street and Norton Street, when required which may cause minor traffic delays.

Machinery used

Heavy and light vehicles including concrete pump trucks, trucks, cranes, dump trucks, loaders, excavators and rollers will be used within the work areas.

How we’re managing impacts

  • Traffic management in place to ensure safe access for all road users and pedestrians, where required
  • Environmental controls in place including live monitoring of noise, dust and vibration.

Contact

Phone: 1800 929 244

Email: inlandrailvic@inlandrail.com.au

Visit: 48a Norton Street on Thursdays 10am–2pm.

Thank you for your patience and cooperation while we carry out these works.


Share: