Works are continuing in Victoria, across 12 sites between Beveridge and Albury, on the Victoria/New South Wales border.
Below is a list of the current works notifications for the Beveridge to Albury section of Inland Rail. The table can be sorted by town and start date.
Town | Start Date | ||||
---|---|---|---|---|---|
Chiltern | Powerline works | Chiltern Railway Station | May 2025 | May 2025 | Read more |
Wangaratta | Completion works | Wangaratta Railway Station | May 2025 | May 2025 | Read more |
Broadford | Traffic changes and bridge works | Hamilton Street bridge | 01 May 2025 | 31 May 2025 | Read more |
Benalla | Site establishment works | Benalla Station Precinct | 01 May 2025 | 31 May 2025 | Read more |
Broadford | Surveys, vegetation removal and site works | Marchbanks Road | 01 May 2025 | 31 May 2025 | Read more |
Wandong | Site establishment and surveys | Multiple locations | 01 May 2025 | 31 May 2025 | Read more |
Euroa | Anderson Street bridge closure and demolition works | Euroa | 01 May 2025 | 31 May 2025 | Read more |
Broadford | Site establishment works and utility relocation | Short Street bridge | 01 May 2025 | 31 May 2025 | Read more |
Seymour | Powerline works | Seymour Railway Station | May 2025 | May 2025 | Read more |
Broadford | Watermain relocation, night works | Short St | 20 May 2025 | 24 May 2025 | Read more |
Euroa | Anderson Street bridge demolition (includes night works) | Anderson Street bridge | 26 May 2025 | 26 May 2025 | Read more |