North of Narrabri to Penneys Road ongoing construction works

Our contractor Trans4m Rail will continue construction works within the rail corridor between the Plant Breeding Institute, north of Narrabri and Penneys Road, Bellata.

Image of completed level crossing and track at Edgeroi

Snapshot

Date

May 2023 - July 2023

Working hours

7am and 6pm, Monday to Sunday

Location

North of Narrabri to Penneys Road

Town
  • Narrabri
  • Bellata
Local Government Area
  • Narrabri Shire Council

Work being done

From Monday 29 May 2023, our contractor Trans4m Rail will continue construction works within the rail corridor between the Plant Breeding Institute, north of Narrabri and Penneys Road, Bellata.

Works will involve:

  • upgrading signaling and communications equipment
  • surveying
  • installing signage, fencing and landscaping
  • commissioning and finishing works.

Low impact activities associated with the works, such as machinery re-fueling, managing environmental controls and traffic control may occur outside of working hours.

What can I expect?

  • Trucks and other vehicles will enter and exit the construction site via multiple access gates
  • construction machinery and equipment operating on site
  • delivery of materials and equipment
  • changed traffic conditions under traffic control.

Machinery used

  • Hi-rail vehicles
  • excavators
  • loaders
  • watercarts.

How we’re managing impacts

Traffic control will be in place and water carts used to assist in managing dust, where required.

Contact

Phone: 1800 732 761
Email: inlandrailnsw@artc.com.au
Post: Inland Rail, GPO Box 14, Sydney NSW 2001