Albury to Illabo site establishment, out-of-hours works, 13 February to 24 March 2025

Inland Rail plans to undertake site establishment and construction works across multiple sites between Junee and Illabo, followed by a statewide track possession.

Snapshot

Date

13 February 2025 - 24 March 2025

Working hours

Ordinary hours: Monday to Saturday 7am-6pm

Track possession hours: 6am, 22 March to 6pm, 24 March.

Location

Multiple locations

Town
  • Illabo
  • Marinna
  • Junee
Local Government Area
  • Junee Shire

Work being done

Site establishment and pre-possession works/activities will commence from Thursday 13 February right up until the track possession.

Track possession will start from 6am, Saturday 22 March, and continue until 6pm Monday 24 March. These works will be continuous, including night works during this period.

Pre and post possession work hours: Monday to Saturday 7am- 6pm.

Pre-possession works planned

Thurs 13 February – Fri 21 March

  • Delivery of plant and equipment using heavy vehicles
  • Signaling works
  • Slashing
  • Survey control densification
  • Contamination testing
  • Clearing and grubbing
  • Earthworks
  • Establishment of our construction zones and laydown areas

Possession works planned

Sat 22 March – Mon 24 March

  • Track works
  • Drainage works including culvert replacements
  • Shoulder reconstruction, resurfacing and destress.

What can I expect?

  • Heavy vehicle movements, earth-moving activities, track works.
  • Some of these works will be noisy. You may hear truck engines and engine noise from machines.
  • Roads may be under traffic control during possession hours.
  • Unfortunately, some construction activities are inherently noisy which cannot be avoided. Properties near the construction site can expect to hear:
    • excavation (activity involving the removal of existing surfaces such as rock, soil, pavement, and other substances
    • movements of heavy vehicles
    • loading, unloading or moving equipment and construction materials.

Vehicle movements

During the works, vehicle movements will be to and from site as well as on site to facilitate earthworks.

Both sites will also be accepting deliveries during site establishment.

Traffic controllers will be available to direct traffic to and from site where needed.

 

 

Machinery used

Equipment used for work includes but is not limited to hand tools including power saws, excavators, loaders, graders, rollers, moxy trucks, truck and dogs, vibrating rollers, track tampers, track regulators, back hoes, cranes, vacuum trucks heavy and light vehicles, generators, lighting towers and other minor plant.

How we're managing impacts

  • Traffic controls will be in place, where required.
  • Water carts will be on-site to wet down areas to assist in managing dust.
  • Use of non-tonal reversing alarms on all equipment and turning off equipment when not in use.
  • Instructing workers to keep noise to a minimum and being respectful of our neighbours.
  • Works will be monitored to ensure compliance with Project Approval Conditions.

Contact

For any concerns or enquiries phone 1800 732 761 or email inlandrailnsw@inlandrail.com.au.

Thank you for your patience and cooperation while we carry out these works.

Works maps:

 

A map showing a work site running along the rail line next to a highway.
Site Works at Illabo.
A map showing a worksite area running along a train track in between two roads.
The site at Marinna.
A map showing a long worksite area running along a rural highway.
The site Between Marinna and Junee.

Share: