Powerline works, Seymour Railway Station, 22 March to May 2025

Inland Rail contractor McConnell Dowell will be conducting powerline works, including removing power cables, installing new poles and running new cables at locations in and around the Seymour Railway station.

Snapshot

Date

22 March 2025 - May 2025

Working hours

7am-7pm Monday to Sunday

Location

Seymour Railway Station

Town
  • Seymour
Local Government Area
  • Mitchell Shire Council

Work being done

To enable the safe running of double-stacked freight trains additional height clearance between the rail and powerlines is required in some locations along the North East rail line including at Seymour Railway Station.

To achieve this, McConnell Dowell will be removing power cables, installing new poles and running new cables at locations in and around the Seymour Railway station.

What can I expect?

  • Works will occur 22 March to May 2025 between 7am-7pm Monday to Sunday
  • Potential night works at the Seymour Railway Station
  • Construction noise during the works
  • Access to the works area will be via the station platform, Railway Place, Dowling Avenue, McIntyre Street and Watson Street
  • Plant and other vehicles entering and exiting the works area
  • Machinery and equipment operating onsite, including a scissor lift on the station platform
  • Delivery of materials and equipment
  • Traffic management for vehicles, pedestrians and rail passengers.

Machinery used

Elevated work platforms, cranes, light towers and light vehicles will be used within the work area.

How we're managing impacts

  • Traffic management on local roads to support plant and other vehicles entering and exiting the works area
  • Traffic management, where required to assist pedestrians at the Seymour Railway Station
  • Potential night works to minimise impacts on Seymour Railway Station passengers.

Contact

For any concerns or enquiries please phone 1800 929 244 or email inlandrailvic@inlandrail.com.au.

Thank you for your patience and cooperation while we carry out these works.