No. 104: Final maintenance/construction works

In the coming months we will be completing the final maintenance/construction works from Parkes to Narromine.

No. 104: Final maintenance/construction works on P2N

Snapshot

Date

October 2020 - January 2022

Working hours

Our standard working hours are 7am to 6pm Monday to Friday and 8am to 1pm Saturdays.

Intermittent out of hours works are 6am to 6pm Monday to Friday and 6am to 6pm Saturdays and Sundays.

Location

Between Parkes and Narromine

Town
  • Parkes, NSW
  • Narromine, NSW
Local Government Area
  • Narromine Shire Council
  • Parkes Shire Council

Work being done

  • fencing the rail corridor
  • hydro-mulching (spraying grass seed) in the rail corridor
  • minor final construction works in the rail corridor
  • returning leased land to landowners

What to expect

These works will be in or around the rail corridor and will not impact road users.

  • construction workers working in the rail corridor with earth moving equipment
  • importing material to and around site with heavy vehicles, cement trucks and light vehicles
  • removal of site storage compounds

Once rail has been installed in each section, the rail will be ‘live’ and construction trains will be intermittently passing across the level crossing.

For your continued safety, please ensure you obey all signage at level crossings.

Machinery used

Use of machinery in the works area, may include:

  • excavators
  • loaders
  • tamping machine
  • dump trucks
  • rollers
  • graders
  • water carts
  • regulators
  • rail saw
  • rail grinders
  • concrete pumps
  • hand tools
  • stressing machine
  • rail clippers
  • vibrating screeds
  • small petrol-powered clipping machines
  • rail tensors
  • light vehicles

Contact

Phone: 1800 732 761

Email: inlandrailnsw@artc.com.au

Post: Inland Rail, GPO Box 14, Sydney NSW 2001