Wirrinya Yard, Start of Construction and Out-of-Hours Works

Inland Rail contractor, Martinus Rail, plans to undertake site establishment and construction works at Wirrinya Yard. Site Establishment will begin from 22 January 2025, with construction works to follow.

Snapshot

Date

22 January 2025 - 24 March 2025

Working hours

Site establishment and ongoing works will run on a rotating 2:1 roster (14 days on with 7 days off) commencing from the 22 January 2025.

Hours of work when the site is rostered on (14 days straight) will be
7am – 6pm Monday to Sunday

A statewide track possession will also take place in March 2025 from Saturday 22 March 6:00am until Monday 24th March 6:00pm, meaning works will be continuous throughout the night for a total of 60 hours.

Location

Wirrinya Yard

Town
  • Wirrinya
Local Government Area
  • Forbes Shire Council

Work being done

  • Cadastral Surveys
  • Establishment of our construction zones, compounds and laydown areas
  • Establishment of construction-only access driveways on Gap Road
  • Slashing
  • Topsoil stripping & grubbing
  • Track works
  • Drainage works
  • Internal fence line realignment
  • Track tamping and realignment

What can I expect?

  • Heavy vehicle movements, earth-moving activities, track works
  • Some of these works will be noisy. You may hear truck engines and engine noise from machines.
  • Use of non-tonal reversing alarms on all equipment and turning off equipment when not in use.
  • Instructing workers to keep noise to a minimum and being respectful of our neighbours.

Machinery used

Equipment used for work includes but is not limited to; hydrema, front end loaders, excavators, tandem trucks, flatbed trucks, rail deliveries including loco, generators, hand tools, flash welding, ballast tamper & regulator, moxy trucks and lighting towers.

Vehicle Movements

During the works, vehicle movements will be to and from site as well as on site to facilitate earthworks.

Traffic controllers will be available to direct traffic to and from site where needed.

How we're managing impacts

  • Traffic controls will be in place, where required.
  • Water carts will be on-site to wet down areas to assist in managing dust.
  • Works programmed to best minimise noise impacts. We will aim to minimise noise from the works.
  • Unfortunately, some construction activities are inherently noisy which cannot be avoided. Properties near the construction site can expect to hear:
    • excavation (activity involving the removal of existing surfaces such as rock, soil, pavement, and other substances
    • movements of heavy vehicles
    • loading, unloading or moving equipment and construction materials

Contact

Thank you for your patience and cooperation while we carry out these works.