Inland Rail’s year of delivery on Beveridge to Albury

Inland Rail has hailed 2025 as a year of major construction delivery for the Beveridge to Albury project, driving the section towards its target of completion by 2027.

Opening the upgraded Wangaratta Railway Station in May marked the completion of the Beveridge to Albury Tranche 1 section of the project before work turned to Tranche 2 with the installation of new higher bridges at Short Street and Hamilton Street in Broadford and construction beginning on pedestrian underpasses at Euroa and Benalla.

Russell Hamilton, Inland Rail Beveridge to Albury Project Director said:

“This year has been one of remarkable progress on the Beveridge to Albury section.

“Eighteen months after contract award, the Beveridge to Albury project is transforming the rail corridor into a future-ready double-stacked freight route.

“With eight active sites and thousands of hours logged, the pace of delivery has been impressive.

“From Wandong to Benalla new tracks, culverts and bridges are redefining connectivity for generations to come.

“We thank the local communities along the alignment for their patience and cooperation as we continue to deliver this transformative project.”

Aerial shot of train station
Major construction is complete at Wangaratta Station, May 2025.

Benalla


 

The transformation of Benalla Station began with the installation of six precast concrete units to form the new pedestrian underpass and laying the tracks above for the new Oaklands line turnout.

Work at Benalla

Check out our progress slider of Benalla – March 2025 to December 2025.

Euroa


 

Works in Euroa saw the demolition of the Anderson Street bridge and the removal of 25,000 cubic metres (m³) of material, 1.7 kilometres of pavement and drainage built for road detours, construction starting on two new pedestrian underpasses and two upgraded large-scale drainage structures.

For the new Euroa station pedestrian underpass, 3,400 tonnes of material was removed, a 59m² base slab poured and six precast concrete units installed to frame the new structure, before it was buried to be unearthed later in construction.

 

The existing Handbury Street pedestrian underpass at Euroa was demolished, 3,200 tonnes of material removed, almost 400m³ of concrete poured and 52 piles drilled to support the new structure.

Work at Euroa

Check out our progress slider of Euroa – May 2025 to October 2025.

Tallarook and Wandong


 

The construction of retaining walls and abutment works have commenced at the Hume Freeway Tallarook site and bridge abutment and retaining walls are complete at Wandong ready for the new bridge to be lifted into place early next year.

Work at Tallarook

Work at Wandong

Check out our progress slider of Wandong – January 2025 to October 2025.

Media enquiries: Phone 1300 196 401 Email: artcmedia@artc.com.au

Inland Rail is a 1,600km freight rail line, now under construction. It will connect Melbourne and Brisbane via regional Victoria, New South Wales and Queensland.