Construction update: Latest Beveridge to Albury progress, September 2025

Inland Rail continues to achieve major construction milestones in 2025.

 

In this video, Beveridge to Albury Delivery Director Scott Anderson shares an update on construction progress in Victoria.

During the September possession, our construction partner John Holland removed the Hamilton Street bridge and lowered the tracks at Broadford, and installed the first sections of the new pedestrian underpass at Benalla.

Works are continuing across the final eight sites between Benalla and Wandong.