Figures show what it takes to bring the Stockinbingal to Parkes section towards completion

The latest employment figures from Inland Rail’s Stockinbingal to Parkes section illustrate how many people it takes to deliver a major rail project like Inland Rail.

With major works now completed on the Stockinbingal to Parkes section and only a few weeks of minor works remaining, February’s verified figures show it took 596 people to complete major works on the section.

This figure is the total number of people directly employed by contractor Martinus Rail working in the rail corridor to deliver the project.

Major works at the Daroobalgie Loop, Lachlan River Bridge, Forbes Station and Wyndham Avenue have now been completed and the number of people needed on site has reduced, reflecting the progress made.

Regional NSW communities will continue to benefit from Inland Rail construction between now and 2027 as construction begins in the Albury to Illabo and Illabo to Stockinbingal sections of the project later this year.

From July 2023 to February 2025 Inland Rail from Stockinbingal to Parkes has led to:

  • 596 people employed, of whom 55 are First Nations
  • 184 local residents employed, of whom 34 are First Nations
  • 60 women employed
  • 39 tradespeople employed
  • 129 local businesses engaged
  • $12.2 million spent with local businesses
  • $427,400 spent with First Nations businesses Australia-wide

Stephen Jones, Inland Rail Executive Director Program Health, Safety, Environment & Sustainability said:

“We have been able to complete major works on the Stockinbingal to Parkes section of Inland Rail thanks to the hard work and dedication of the workers and businesses who have been supporting us.

“We have a stated goal of delivering Inland Rail south of Parkes by 2027 so it is important to be able to finish major works on this section, and we can only be as successful as the teams on the ground putting in the hard yards.

“It is demanding work to upgrade rail infrastructure – it requires accuracy, safety and physical effort, often in testing conditions and sometimes while wearing hot and heavy protective equipment.

“I would like to express my gratitude to the many locals who have worked on the Stockinbingal to Parkes section, some of whom have joined the industry through the Inland Rail Skills Academy.

“The skills which have enabled these local workers to deliver this section safely and on time will also be of enormous benefit on other parts of Inland Rail when they go into the construction phase later this year.

“Inland Rail is not just about helping the Australian economy, it is also about delivering ongoing opportunities and benefits at a local level.”

 

CAPTION: The latest employment figures on the Stockinbingal to Parkes section of Inland Rail illustrate how many people it takes to deliver one section of the 1,600km rail project.

A worker wearing a heavy welding helmet cuts steel mesh at a rail worksite
Media enquiries: Phone 1300 196 401 Email: artcmedia@artc.com.au