Progress


The Victorian section of Inland Rail includes upgrading 262km of existing rail track between Beveridge, north of Melbourne, and the Victoria-NSW border at Albury-Wodonga.

Works are happening at 12 sites along the North East rail line, and are being delivered in two parts, called ‘tranches’.

VIDEO: Hear from Beveridge to Albury Delivery Director David McGranaghan about what’s on the horizon for Inland Rail in Victoria for 2026.

Project Stages

Beveridge to Albury Tranche 1

On completion of construction, each project is commissioned by ARTC and regulatory bodies to ensure the infrastructure has been delivered according to its design and is safe to operate.

We…

Learn more

Beveridge to Albury Tranche 2

Once a construction contract is awarded, the construction contractor conducts further environmental and technical investigations to validate and enhance the existing reference design.

Early works, such as establishing construction material…

Learn more

Explore project stages

Tranche 2 Construction Progress


John Holland is our construction partner for Tranche 2 works. Construction has started and will be undertaken across eight sites in Benalla, Euroa, Seymour, Tallarook, Broadford and Wandong.

Inland Rail construction in Victoria will be completed in late 2027.

We’re tracking the B2A Tranche 2 team’s progress against completion targets across key project areas:

 

 

Benalla

10%

Station modification

 

Euroa

15%

Station modification &
vehicle underpass

Hume Hwy, Seymour

6%

Track lower

 

Hume Hwy, Tallarook

8%

Track lower

 

Wandong

11%

Bridge replacement

 

Short St, Broadford

15%

Bridge replacement &
track lower

Hamilton St, Broadford

53%

Bridge replacement &
track lower

Marchbanks Rd, Broadford

9%

Bridge replacement

 

Construction progress at September 2025.

Tranche 1 Construction Progress


McConnell Dowell was our construction partner for Beveridge to Albury Tranche 1 works. Construction occurred at Glenrowan, Barnawartha North, Wangaratta and Seymour. Works were also undertaken to relocate tracks, raise signal gantries and modify overhead powerlines along the North East rail line to provide sufficient clearance for double-stacked freight trains.

Construction on the Beveridge to Albury Tranche 1 sites is now complete.

Glenrowan

100%

Beaconsfield Parade bridge
replacement

Barnawartha North

100%

Murray Valley Highway
track lower

Wangaratta

100%

Station Precinct
modification

Wangaratta

100%

Green Street bridge
replacement

Seymour

100%

Seymour-Avenel Road bridge
replacement